Home MenuWest Glendale ADA Curb Ramp Installation and Sidewalk Repair Phase I
Specification No. 4006
Project Location
The project locations are in Maintenance Districts 4, 8, 9, and 10. Please see project location map below.
Scope of Work
The project scope of work includes the following:
- Selective removal, repair, and reconstruction of damaged curbs, gutters, sidewalks, driveways, cross gutters, and alley aprons.
- Selective removal, repair, and reconstruction of damaged asphalt and Portland cement concrete pavements.
- Installation of new ADA compliant curb ramps where none existed.
- Modification and reconstruction of existing ramps to meet current ADA standards.
Phase
The project is in the construction phase.
Construction Schedule
Construction is tentatively scheduled from August 2025 to end of December 2025 barring any unforeseen circumstances.
Traffic Impacts
During the repair of damaged sidewalks and construction of ADA improvements, the sidewalk will be closed and traffic will be affected temporarily.