San Fernando Road Beautification Project Phase II

Print
Share & Bookmark, Press Enter to show all options, press Tab go to next option

Project Location

The project is located on:

San Fernando Rd B exh 1 ph 2 July 1

 Exhibit 2 SFR Phase 2 Planting sept 25 jpg

Scope of Work

  • Surface grinding and placement of approximately 1.6 centerline miles of asphalt rubber hot mix (ARHM).
  • Selective removal, repair, and reconstruction of damaged curbs and gutters, sidewalks, driveways, cross gutters, alley aprons, and bus pads.
  • Modification and reconstruction of approximately existing curb ramps to meet current ADA standards.
  • Adjustment of existing manholes and water meters to finished grade.
  • Removal and replacement of existing traffic striping and pavement markings.
  • Improve intersections with curb extensions or refuge islands for pedestrian safety.
  • Planting of new street trees.
  • Installation of drywells and bioswales.
  • Bus stop improvements.
  • Traffic signal modifications and upgrades.
  • Installation of landscape parkway

Community Open House

Please scan the QR code to take a short survey

SFR qr code 10-25

When: Monday, October 20, 2025

Time: 4:00pm to 7:00pm

Location: Griffith Manor Park Community Room, 1551 Flower St., Glendale, CA 91201

Phase

The Project is currently in the design phase.

Construction Schedule

Construction is tentatively scheduled from Fall 2026 to end of Summer 2027 barring any unforeseen circumstances.

Construction Updates

Check back at the start of the project!

Traffic Impacts

Check back at the start of the project!

Construction Photos

San Fernando rd July 1 2025

 San Fernando Rd 3

Above photos represent Phase I post-construction for reference.

Contact Information:

Huang Zheng, P.E., Civil Engineer II

(818) 937-8250 

hzheng@glendaleca.gov

Armen Avazian, P.E., Principal Civil Engineer

(818) 548-3945

aavazian@glendaleca.gov