City of Glendale, CA
Home MenuLa Crescenta Avenue Rehabilitation Project
Project Location
- The project location is on La Crescenta Avenue between N. Verdugo Road and Montrose Avenue. Please see project location map below.
Funding Sources
The project is funded with Measure M and R, Gas Tax and Sewer Fund monies.
Scope of Work
- Sewer Improvements
- Reconstruction of curb and gutters, alley aprons, driveways and sidewalks
- Pavement replacement
- ADA-compliant curb ramps
- Intersection realignment
- Removal of a travel lane in each direction, addition of a center two-way left turn lane, and installation of new protected bicycle lanes and buffered bicycle lanes
- Traffic signal and fiber optic improvements
- Installation of bio-retention facilities
- Reflective pavement installation
- Installation of new traffic signing and striping, including creative crosswalks
- Tree planting
Please click here to view the Drywell Fact Sheet
Phase
- The Project is completed. View the latest Press Release
Construction Schedule
The La Crescenta Avenue Rehabilitation Project has completed full corridor paving ahead of schedule, with work finished on April 30, 2026. Final project activities will continue through May, beginning with traffic signal modifications the week of May 4.
During the week of May 11th, crews set up the proposed striping configuration. Temporary markings will maintain two lanes in each direction to keep traffic moving.
Final striping was scheduled for May 18th, installing one travel lane in each direction with a center two-way turn lane. This work will be completed using rolling traffic control, allowing traffic to flow as crews move along the corridor. Message boards will be updated to alert drivers to the new lane configuration.
All scheduled work is subject to change due to weather or unforeseen conditions. Construction is expected to be completed by July 2026.
Tentative Construction Schedule:
• May 2026: Installation of Street Signs & Striping including bike lanes
• June 2026: Installation of decorative crosswalks at signalized intersections and reflective pavement on Paloma Avenue and other punch list items
Traffic Impacts
During the construction period, detours, intermittent lane closures, and traffic delays are expected on the following streets:
Location and Dates
La Crescenta Avenue: Travel lanes may be closed intermittently between 5/18/2026 thru 6/18/2026 (excludes weekends and holidays)
• La Crescenta Avenue from Verdugo Rd to Montrose Ave: One travel lane may be closed intermittently between 5/11/2026 thru 5/22/2026 (excludes weekends and holidays)
• Paloma Avenue from La Crescenta Ave to Downing Ave: Travel lanes may be closed intermittently between 6/15/2026 thru 6/16/2026 (excludes weekends and holidays)
• La Crescenta Avenue at Shirlyjean St, Roselawn Ave, Oakmont View Dr, and Piedmont Ave: Travel lanes may be closed intermittently between 6/17/2026 thru 6/18/2026 (excludes weekends and holidays)
Description of Work
• Contractor will perform preparatory work for traffic signals.
• Contractor will perform work for roadway striping and signage.
• Contractor will perform work for installation of reflective pavement.
• Contractor will perform work for installation of decorative crosswalks.
For frequently asked questions, please refer to the project Fact Sheet.
Thank you for your continued patience and understanding throughout the La Crescenta Avenue Rehabilitation Project.
The City remains dedicated to completing this project with exceptional quality and to the highest standards. We truly appreciate your patience and cooperation as we work to deliver lasting improvements to this corridor for the entire community.
For the latest project updates, please visit GlendaleCA.gov/LaCrescentaRehab or contact us at the information below.
Please observe posted construction signage and drive safely near construction zones.
*Construction activity and closures are subject to change.
Construction Photos
Project Renderings/Simulation
Traffic Simulation Video
La Crescenta and Paloma Ave
La Crescenta and Roselawn Ave
La Crescenta and Piedmont Ave
Community Outreach and Stakeholder Engagement
Public Hearing for the Crosswalk Removal at the Intersection of La Crescenta Avenue and Roselawn Avenue
- Click here to view the Notice of Crosswalk Removal on La Crescenta Avenue and Roselawn Avenue
- Click here to view the Responses to Questions/Comments Received During the Public Hearing Discussion
Figure 1: Proposed Intersection of La Crescenta Avenue and Roselawn Avenue
Community Meeting
First Community Meeting (February 17, 2022)
- Click here to view the Community Meeting Notification
- Click here to access the Recorded Virtual Community Meeting
- Click here to view the Responses to Questions/Comments Received During the Virtual Community Meeting on 2/17/2022
Second Community Meeting (March 8, 2023)
- Click here to view the Community Meeting Notification
- Click here to view the Responses to Questions/Comments Received During Virtual Community Meeting on 3/8/2023
Montrose Shopping Park Association
- Public Works Engineering staff conducted a Virtual Presentation to the Montrose Shopping Park Association Board on March 18, 2022.
Whiting Woods Property Owner’s Association
- Public Works Engineering staff conducted a Presentation to the Whiting Woods Property Owner’s Association on June 4, 2022.
Crescenta Valley Chamber of Commerce
- Public Works Engineering staff conducted a Virtual Presentation to the Crescenta Valley Chamber of Commerce on June 9, 2022.
Crescenta Valley Community Association
- Public Works Engineering staff conducted a Virtual Presentation to the Crescenta Valley Community Association on June 23, 2022.
Sycamore Woods Community
- Public Works Engineering staff conducted a Presentation to the Sycamore Woods Community Members on June 25, 2022.
Oakmont Country Club
- Public Works Engineering staff conducted a Presentation to the Oakmont Country Club Board on June 29, 2022.
Oakmont Woods Association
- Public Works Engineering staff conducted a Presentation to the Oakmont Woods Community Association on June 29, 2022.
Glendale Police Department
- Public Works Engineering staff coordinated with the Glendale Police Department to conduct additional outreach efforts to various Neighborhood Block Captains and Businesses in the North Glendale area to inform stakeholders about the project and to provide feedback.
- Please click here to view the postcard.
Crescenta Valley Town Council
- Public Works Engineering staff conducted a Virtual Presentation to the Crescenta Valley Town Council on August 18, 2022.
Transportation and Parking Commission
- Public Works Engineering staff presented the project to the Transportation and Parking Commission on August 2022.
- Click here to access the Recorded Transportation and Parking Commission Meeting and Agenda
City Council
First Council Meeting
- Public Works Engineering staff presented the project to the City Council in October 2022 to select a Bicycle Facility Alternative.
- Click here to access the recorded City Council Meeting and Agenda.
Second Council Meeting
- Public Works Engineering staff presented the project to the City Council in February 2024 to advertise for construction bids.
- Click here to access the recorded City Council Meeting and Agenda.
Contact Information
Public Works Engineering: (818) 548-3945
Public Works Project Manager: Rustom Tavitian, P.E. Email
