Fiscal Year 2020-21 Street Resurfacing and Sewer Repair Project

Print
Share & Bookmark, Press Enter to show all options, press Tab go to next option

Project Location

Project Location Map Updated 6.10.21 - Map1

Project Location Map Updated 6.10.21 - Map2

 

Project Location Map Updated 6.10.21 - Map3

  • Central Avenue - Dryden Street to Kenneth Road
  • Loraine Street - Valley View Road to Central Avenue
  • Valley View Road - Cumberland Road to E'ly Terminus
  • Sherlock Drive - Mountain Street to City Limit
  • South Street - Virginia Avenue to Concord Street
  • Cleveland Road - Glenwood Road to Olmsted Drive
  • Norton Avenue - Olmsted Drive to Kenneth Road
  • Virginia Avenue - Kenneth Road to Sunset Road
  • Spencer Street - Pacific Avenue to Dorothy Drive
  • Dorothy Drive - Spencer Street to Kenneth Road
  • Columbus Avenue - Dryden Street to Stocker
  • Fischer Street - Maple Street to Colorado Street
  • Griswold Street - Maple Street to Colorado Street
  • Chevy Chase Library and Fire Station 23 sewer lateral replacement
  • Melwood Drive - Remah Vista Drive to Southerly Terminus
  • Montrose Community Park
  • Sewer repairs through the City

Scope of Work

  • Selective removal/reconstruction/surface grinding of deteriorated pavement and placement of asphalt concrete pavement;
  • Application of crack sealing material and emulsion aggregate slurry (Slurry Seal Type III);
  • Placement of asphalt rubber hot mix pavement (ARHM) over asphalt leveling course;
  • Selective removal and repair of broken and damaged sidewalks, curbs, curbs and gutters, cross gutters, driveway approaches, local depressions, alley aprons and bus pads;
  • Installation of new curb ramps meeting current Federal ADA requirements;
  • Removal and planting of new trees and pruning of tree roots;
  • Adjustment of existing utilities to finished grade;
  • Removal and replacement of existing traffic striping and installation of new striping;
  • Speed hump installations on Fischer Street and Griswold Street;
  • Slope stabilization and road reconstruction on Melwood Drive;
  • Sewer lateral removal and replacement at Chevy Chase Library and Fire Station 23;
  • Sanitary sewer point repairs and lining at various locations throughout the City; and,
  • Electrical infrastructure improvements at Montrose Community Park.

Phase

  • Construction

Construction UpdatesConstruction Notification

Community Meeting

1.28.21

FY 20-21 - Community Meeting Presentation

Construction Photos

4265238199801684822

-4381508365985840496

2508632079533967667

FY 2020-21 Street Resurfacing and Sewer Repair Project Exhibit One Project Location Map

FY 2020-21 Street Resurfacing and Sewer Repair Project Exhibit Two Project Location Map

IMG_4857IMG_6374

IMG_5647IMG_4766IMG_564820211202_194118929_iOS IMG_5928

intersection stop sign

Contact Information

  • Public Works Engineering, (818) 548-3945
  • Public Works Project Manager: Viktoriya Pakhanyan, Email