La Crescenta Avenue Rehabilitation Project
The La Crescenta Avenue Rehabilitation Project has made significant progress in recent months. Major safety improvements have been implemented, including the realignment of intersections and enhanced pedestrian accessibility. Additionally, the contractor has completed installation of bio-retention facilities and critical infrastructure upgrades, including traffic signal and fiber optic systems, as well as the upsizing of existing sewer mainline.
While most improvements are complete, certain key elements—including roadway resurfacing, striping, and decorative crosswalks—are scheduled for completion by June 2026, barring any additional unforeseen circumstances.
The revised schedule is due to utility relocation work required by GWP Electric, Charter, and AT&T for the Twelve Oaks development site on La Crescenta Avenue and Sycamore Avenue.
Tentative Construction Schedule:
• April 2026: Roadway resurfacing
• May 2026: Roadway striping and utility adjustments
• June 2026: Installation of decorative crosswalks and reflective pavement on Paloma Avenue
Interstate 5 Burbank Pavement Rehabilitation Project
Start Date: January-2026 Finish Date: Summer-2027
Extended weekend closure on SB I-5 scheduled from 10 p.m. Friday, March 13, through 5 a.m. Monday, March 16
Description of Work: Caltrans Project
- Replacing and restoring damaged and unstable pavement within the project limits
Caltrans Contacts: Colleen Park, Public Information Officer colleen.park@dot.ca.gov
Click the link below for more information with regards to detours and additional closures:
Caltrans Link: Interstate 5 Burbank Pavement Rehabilitation Project | Caltrans