Update: As of April 30, 2025
Tentative Construction Schedule:
- May 1 - 30: Contractor performing sewer upgrades between Verdugo Road and Paloma Avenue.
-
May 1 - 15: Contractor performing fiber optic installation at:
- La Crescenta Avenue between Honolulu Avenue and Montrose Avenue
- Montrose Avenue between Ramsdell Avenue and La Crescenta Avenue
- At the intersection of Pennsylvania Avenue and Honolulu Avenue
- May 1 - 15: Contractor performing potholing and utility locating for traffic signal upgrades.
- May 15 - 30: Contractor performing traffic signal conduit installation at various locations.
Past Updates
As of March 18, 2025:
As of March 10, 2025:
- March 31: Contractor mobilization and preparatory work
- April 2 - 4: Survey for sewer main upgrades
- April 7 - 18: Contractor to perform potholing for utilities
- April 21 - May 30: Contractor to complete sewer upgrades between Verdugo Rd. and Paloma Ave.
Project Scope
The La Crescenta Avenue Rehabilitation Project focuses on enhancing safety, mobility, and infrastructure through extensive corridor improvements. Key upgrades include new traffic control devices, pavement resurfacing, bicycle facilities, stormwater infiltration systems, sewer capacity enhancements, and traffic signal modifications. Many improvements stem from community input gathered during public meetings.
Core elements of the project include:
- Resurfacing 1.7 miles of street pavement, repairing 4,900 linear feet of curbs and gutters, and upgrading 44,500 square feet of sidewalks, driveways, and alley aprons.
- Constructing and modifying 59 ADA-compliant curb ramps and planting 21 new street trees.
- Upgrading sewer systems, realigning six intersections, and modifying traffic signals at key locations.
- Adding fiber optic infrastructure, a new traffic signal, pedestrian hybrid beacon, and mid-block signalized bicycle crossing on La Crescenta Avenue.
- Installing drywell, bio-retention facilities, and reflective pavement for stormwater management and sustainability.
- Repurposing travel lanes for a center two-way left-turn lane to improve traffic flow and safety.
- Installing 17,000 linear feet of protected and standard bike lanes, bicycle-friendly catch basin grates, and four creative crosswalks.
- This project emphasizes accessibility, safety, and sustainable mobility for the community.
Click here for more information on the La Crescenta Avenue Rehabilitation Project.
Community Outreach
There has been extensive community outreach to include a number of community meetings, public hearings, HOA outreach, business outreach, email and phone interaction, mail, reports in the local Crescenta Valley Weekly Newspaper, and mailers.
See the outreach history here.
With the project beginning in early March 2025, there will be additional updates and continued community participation.