Park Manor 1290 Reservoir Slope Repair and Debris Mitigation

Print
Share & Bookmark, Press Enter to show all options, press Tab go to next option

Background

The Park Manor 1290 Reservoir is a reinforced concrete, potable water storage reservoir serving the City’s 1290 water pressure zone. Storm water erosion has occurred at the top of the reservoir slope embankment. This project will stabilize the reservoir embankment and restore the storm water catch basin adjacent to the reservoir.

Scope of Work

The work primarily includes restoring and stabilizing the existing reservoir embankment. Installing a debris barrier at the base of the embankment to enhance debris flow aiding in the catch basin clearance and maintenance.

Project Schedule

The design of the project is completed.  Construction is expected to begin in February 2025 and will last approximately 8 months.

Contact Information

For specific questions about the project, contact:

Coleman Johnson
ColemanJohson@glendaleca.gov
(818) 551-6909

If you would like to be contacted via email for project updates and information, contact:

Atineh Haroutunian
Aharoutunian@glendaleca.gov
(818) 548-3381