Utility Operations Center Parking Lot - Carport Solar Project

Print
Share & Bookmark, Press Enter to show all options, press Tab go to next option

Project Details

The estimated capacity of the Utility Operations Center Parking Lot – Carport Solar Project is 411 kW. This solar array is estimated to produce approximately 650 thousand kWh/year of clean solar energy. That is equivalent to powering 91 homes annually. The Utility Operations Center Parking Lot is the employee parking lot for the GWP Power Plant, which is located adjacent to where the Verdugo Wash empties into the Los Angeles River. 

For the Utility Operations Center Solar Project to be successful, there are 3 trees in the parking lot that must be removed. More information will be provided once the plan is finalized.

Project Activity

November 2024: Completed dig alert locating for underground utilities.

December 2024: Solar canopy plan sets submitted to GWP for review. Confirmed revisions to accommodate equipment access clearances and turning radiuses for water treatment facility. 

February 2025: Updated solar canopy plan sets with revised location for solar switchgear and transformer. Submitted plan sets to GWP Engineering for plan review. 

April 2025: Completed distributed generation service spot drawing for electric switchgear and transformer pad.