Scope of Work
The estimated capacity of the GWP Perkins Building – Rooftop Solar Project is 184 kW. This solar array is estimated to produce approximately 300 thousand kWh/year of clean solar energy. That is equivalent powering 41 homes annually.
Project Status
October 2024: Completion of all plan reviews and permit issued.
November 2024: Project mobilization and material delivery completed.
December 2024: Roof repairs completed.
January 2025: Completed solar panel and inverter installation.
February 2025: Completed switchgear installation and electrical substructure construction.
March 2025: Completed interconnection to electric distribution grid, system commissioning and testing.
April 2025: Ribbon cutting ceremony with City Council, City Manager, GWP Leadership, and Solar Optimum.