City of Glendale, CA
Home MenuBiogas Generation Project Timeline/Milestones
Project Timeline
| Key Project Schedule Dates | |
|
Issued FNTP (Full Notice to Proceed) to Generator Supplier, WES (Western Energy Systems) |
April 2023 |
| Executed Contract and Issued FNTP to EPC (Engineering, Procurement, Construction) Contractor, ACCO Engineered Systems |
May 2023 |
| Engineering Design | June 2023 thru March 2024 |
| Site Mobilization |
September 2023 thru December 2023 |
| Construction |
November 2023 thru March 2025 |
| WES Bio-Gas Engine Delivery |
June 2024 |
| Startup, TAB (Testing, Adjusting, and Balancing), and Commissioning |
March 2025 thru June 2025 |
| Substantial Completion |
June 2026 |
Project Milestones
|
Activity |
Date |
Status |
|
IS/MND Comment Review Period |
August 30, 2017 – November 9, 2017 |
Completed |
|
Submitted Initial Study/Mitigated Negative Declaration (IS/MND) to State Clearinghouse, LA County Clerk, and sent Notice of Intent letter to local stakeholders and community. |
August 30, 2017 |
Completed |
|
Notice of Availability of Initial Study/ Mitigated Negative Declaration (IS/MND) posted in local newspaper |
August 30, 2017 |
Completed |
|
Application to City of Glendale Planning Department Submitted |
July 31, 2017 |
Completed |
|
City qualifies four EPC contractors to be able to submit Proposal to Engineer, Procure and Construct the balance of plant:
|
October 2, 2017 |
Completed |
|
City receives response to RFQ |
July 28, 2017 |
Completed |
|
RFQ Response Deadline 2:00 P.M. PST |
July 28, 2017 |
Completed |
|
City issues Request for Qualifications (RFQ) to Proposers to Engineer, Procure, and Construct the balance of plant |
June 14, 2017 |
Completed |
|
City Council authorized to award contract to purchase Power Island and Major Equipment to Western Energy Systems |
June 13, 2017 |
Completed |
| Planning Commission Hearing to consider adopting MND | March 31, 2018 | Completed |
| Contract executed with consultant to prepare EIR | February 7, 2019 | Completed |
| Initial Study/Notice of Preparation of EIR/Public Scoping Meeting | March, 2019 - April, 2019 |
Completed |
| Draft EIR Preparation | April, 2019 - September, 2019 | Completed |
| Draft EIR Public Comment Period | September, 2019 - November, 2019 | Completed |
| Response to Draft EIR Public Comments | January, 2019 |
Completed |
| Presentation of Draft EIR to Planning Commission for Certification | February, 2020 |
Completed |
| Sustainability Commission & GWP Commission Joint Special Meeting | September 2, 2021 | Completed |
| City Council Certification of EIR for the Scholl Canyon Landfill Biogas Renewable Generation Project (Biogas Project) and approval of the Conditional Use Permit (CUP) and Special Recreation (SR) Permit | November 30, 2021 | Completed |
| GWP's Owner's Engineer, Worley Group Inc. (Worley), undertook the RFQ and the subsequent RFP process to identify the most overall qualified EPC contractor in terms of price and technical competence. | January 2022 | Completed |
| Staff presentation to City Council to execute amendment #1. Full notice to proceed for the second and final phase of the Biogas project. | September 20, 2022 | Completed |
| Community Open House for the Scholl Canyon Biogas Renewable Generation Project | November 30, 2022 | Completed |