The Final Environmental Impact Report (EIR) for the Proposed Grayson Repowering Project can be found here.

For more information about this project, visit GraysonRepowering.com

Providing Reliable Power

 

Click here to view the AQMD Public Meeting to Discuss GWP's 2015 Health Risk Assessment of the Grayson Power Plant

Click here to view the Power Point from GWP's Special Commission Meeting on the Grayson Repowering Draft Environmental Impact Report.

Glendale Water & Power faces significant decisions over the next few years in order to:

1. Maintain reliable services

2. Comply with state regulations regarding renewable energy supplies and greenhouse gas emissions and

3. Keep rates affordable to Glendale ratepayers. 

The City's Grayson Power Plant is experiencing an increasing frequency in unplanned and forced outages. These outages threaten local reliability and prevent the generation of renewable energy from landfill gas from Scholl Canyon. GWP has one major interconnection through the Air Way Substation to import energy from remote generation. These imports rely on available transmission, but the transmission grid has contractual and physical limitation to bring in all the energy that is necessary to provide reliable service to Glendale. Additionally GWP has outside generation sources that are planned for retirement or contract termination. 

The Integrated Resource Plan addresses all of these issues and guides future decisions for the Grayson Power Plant. If the City Council elects to proceed with the repowering of the Grayson Power Plant, the City can meet all state environmental requirements associated with the construction of a large power project, prepare for demolition, and ensure proper and safe deconstruction, construction and commissioning of a new plant. 

Frequently Asked Questions:

Proposed Grayson Repowering Project Frequently Asked Questions


Are you expanding the Grayson Power Plant?

No, Glendale Water & Power (GWP) is not proposing to expand the Grayson Power Plant. The driving force for replacing the obsolete Units 1-5 and 8* at the Grayson Power Plant is to ensure a reliable electric supply for the citizens and residents of the City of Glendale. A majority of the facilities located at the Grayson Power Plant were completed between 1941 and 1977, and must be replaced.  

We are proposing to rebuild substantial portions of the plant by taking old generating units out of commission, dismantling them, and building new, modern units in their place. This process is called repowering. The new repowered units will be cleaner, more energy efficient, and will greatly increase the reliability of the Glendale’s power grid.

* units 6 and 7 were retired several years ago and dismantled. Unit 9 is about 15 years old and will continue to operate.

How is GWP going to pay for the repowering of the Grayson Power Plant?

GWP is proposing to finance the repowering project through the issuance of revenue bonds. GWP sells bonds to finance capital projects, and the payments for the GWP bonds are covered by the revenue that GWP receives from its customers based on its rate schedule. The tax revenues that the City receives are not used to pay off GWP bonds. The final cost will not be determined until the detailed design is finalized.

Is GWP repowering Grayson to generate excess power in order to sell it for profit?

We are proposing to repower the plant to meet the City’s load demand and to ensure that there is a reliable source of power for Glendale. GWP is not repowering to sell energy for a profit. The capacity of the Grayson repower was driven solely by the reliability needs of Glendale and minimizing rate impacts to GWP customers. GWP is a publicly-owned utility and our mission is to provide clean and reliable power to the residents and businesses of Glendale.

Will potable water be used as part of the repowered Grayson Plant?

The Grayson Power Plant would use recycled water for all process and cooling water requirements. The main use for recycled water includes boiler water makeup, cooling tower makeup, turbine power enhancement and cleaning, and NOx control for the simple cycle units. Recycled water would also be used for Unit 9 in place of potable water currently being used. The use of recycled water would eliminate the need for 20 acre-feet of ground water from wells in Glendale and 41 acre-feet of potable water currently being used, which is also water efficient and helps improve the City’s overall water conservation efforts. 

California’s cap and trade program requires all power producers to pay a cost per ton of CO2 emitted. Is the cost being underestimated?  

The cost of greenhouse gas credits would be incurred by Glendale whenever they use electricity from fossil fuel resources, whether GWP generates it or it is imported over the transmission system. Fossil fuel resources will be required until systems of energy storage have been proven on a utility scale for a utility such as GWP. The operating costs would therefore be incurred either way. Intermittent renewable purchase contracts also include a portion of fossil fuel generation.

Does the Grayson Power Plant sit on a mapped Liquefaction Hazard Zone? 

Like much of the Glendale area, the Grayson Power Plant site is located within a liquefaction hazard zone. A site-specific geotechnical study for the repowering project was performed and included analysis of both seismic and liquefaction risks. The geotechnical study included recommendations for project design in conformance with applicable building codes, which include considerations for seismic and site-specific liquefaction hazards. 

The site has been the home to the City’s local generation for over 75 years and has been subjected to several major earthquakes, including the Sylmar and Northridge earthquakes. Notably, GWP has been able to restore electricity to its customers faster than any other nearby city or Southern California Edison, in part due to having local units at Grayson that were either already operating or were started up, due to seismically-induced loss of transmission imports. 

Why can’t GWP just have solar panels and batteries to power Glendale?

Utilizing solar power alone, whether generated locally or imported, would require a significant storage system to be built to “time shift” enough energy to cover the approximately 65% of the hours that the sun is shining (the 65% value considers the variability of solar energy while the sun is shining). Such a system is would be larger than any projects currently being contemplated or constructed to date, and is estimated to cost significantly more than the proposed project. As with all energy projects, battery storage projects also have ongoing costs, in this case the periodic replacement of the batteries and the efficient recycling of batteries. 

If solar power imported over transmission lines (along with other carbon-free imports over those same transmission lines) was relied upon as the source of power, most of it would be consumed during the daytime, leaving little, if any, for charging the batteries. During the evening, when the transmission capacity exceeds the GWP load, solar power is not available. Thus, the batteries would be charged using non-solar carbon-free resources, and if they were not sufficient, then other fossil fuel resources.

For a utility scale solar power plant located within Glendale, a large site would be needed to generate sufficient energy to serve the daytime load and charge the batteries.  For each megawatt of solar generation installed, approximately 4 to 6 acres are required. To provide the 262 MW that would be required to replace the units that would be lost at the Grayson Power Plan would require approximately 1,310 acres, or approximately 2 square miles. Such a large space is not available within Glendale.

Rooftop solar is another potential source of solar energy, and GWP provides incentives to Glendale homeowners to install solar power on their roofs. Currently, there are approximately 1,344 solar systems installed in the City, totaling 12.2 MW.  Those systems are estimated to generate approximately 16.5 MWh of energy. However, the City cannot count on solar generation on private residential and commercial properties as it does not have control over these systems. 

Solar energy sources do not necessarily need to be located within the City’s limits. By freeing up transmission which would occur as the result of the Grayson Repowering Project, it would allow the City to either purchase or own solar outside the City’s limits and transmit the energy into the City’s electrical grid via the existing transmission lines.

GWP is pursuing the Grayson project because the need exists for another source of power to supplement the solar energy that could be utilized, GWP’s transmission import limitations, the necessity to be capable of dealing with the loss of a transmission line, and the need to add capacity as needed due to the intermittency of renewable energy (to balance out and manage the fluctuating power flows), all while still ensuring a reliable supply of electricity.

Can Scholl Canyon be used as a solar site?

GWP partnered with a private developer two years ago to study the possibility of developing a solar project at Scholl Canyon. The developer determined that the site constraints at Scholl Canyon made it unsuitable for solar development. For example, the existing environmental control systems for the landfill are required even for a closed landfill (these systems gather methane gas that would otherwise escape to the environment, a gas that has a global warming potential 21 times greater than CO2). Those systems require continued access, which consequently limits the land available for solar panels. In addition, the landfill is subject to significant settlement, which would take the solar panels out of alignment, as well as complicating the electrical gathering system design, necessitating regular rebuilding and realignment.

Will the repowered plant increase air pollution in the area?

The permitted emissions from the Grayson Repower project will be less than the permitted emissions from the existing Grayson Power Plant.

GWP developed emissions estimates for the Grayson Repower to use as a basis for permitting. The permitting process is based in part on the worse case daily emission and peak season monthly emissions coupled with the need to provide sufficient starts and operating hours for possible contingencies. Even with these conservative estimates, the permitted emissions from the repowered plant would be less than the permitted emissions from the existing plant.

The permitted emissions from the repowered plant would be greater than recent historic actual emissions from the existing plant due to the reduced operations resulting from the declining availability of the existing units. However, the increase in emissions is below the mass emission levels that South Coast Air Quality Management District (AQMD) considers to be significant. In addition, mitigating this concern are two considerations:

  1. Actual operations are expected to be less than what is being permitted and assumed for analysis in the Draft Environmental Impact Report, reducing the actual change in anticipated emissions.
  2. Mass emission levels (lb/day) serve only as a coarse indication of the true impacts of a project. For the Grayson Repowering project, we conducted extensive air quality impact analyses and health risk assessments in accordance with methodologies that are recommended and approved by both South Coast AQMD and US Environmental Protection Agency (EPA) based upon both maximum peak season and annual emissions. Those refined analyses demonstrate that the impacts on ambient air quality and public health are below levels of significance. All increases in pollutants such as NOx, VOC, PM10, SOx are further mitigated by offsetting 100 percent of the emission increase, plus another 20 percent, pursuant to South Coast AQMD regulations.    

Greenhouse gas emissions (CO2) are assessed on a global basis. Greenhouse gas emissions from the project will be offset through the purchase and surrender of greenhouse gas credits to ensure that the total level of greenhouse gasses continues to decline in accordance with California policy and regulations.

Demolition of the existing facility and soil remediation will take 9 months. How are you making sure no contaminants if any are emitted into the air?

During demolition of the existing facility, waste removal plans will be developed and implemented to ensure that no lead or asbestos or other known contaminants are emitted into the atmosphere. Demolition will be done in accordance with applicable federal, state and local requirements. These requirements address containment and handling of materials, as well as a monitoring plan to ensure compliance. These requirements are not specific to the demolition of a power plant; they apply to all demolition work. The contractors we will use are licensed to do this type of demolition and meet these requirements.