Project Overview:

The project allows the City of Glendale to have its first-ever co-located Beeline and Dial-A-Ride facility which will help improve operations by locating Administration, Operations and Maintenance on one campus. The Facility provides secured vehicle parking for the transit fleet of 37 buses, 9 demand response vehicles, non-revenue vehicles, and staff, with room to grow.

Bldg for sign c

Timeline (this timeline will be updated as more information becomes available):

  • March 6, 2018 - Groundbreaking
  • April 1, 2018 - Site preparation and lot securement
  • April 1-July 2018 - Grading and underground utility installation
  • August 2018 - Construction of building begins
  • Late 2019 - Estimated Grand Opening